"PRIDNIPROVSKA BIOTES", TOKMAK

"PRIDNIPROVSKA BIOTES", TOKMAK

General contractor. Turnkey construction of a combined heat and power plant with an electric capacity of 8.6 MW using biofuel (wood chips).

"SIVERSKA TES" LLC SLAVUTICH

"SIVERSKA TES" LLC SLAVUTICH

General contractor. Turn-key construction of an energy infrastructure facility - a combined heat and power plant (CHP) with an electric capacity of 12.5 MW on biofuel (wood chips).

FACTORY OF MDF PLATES KOROSTEN ZHITOMIR REGION.

FACTORY OF MDF PLATES KOROSTEN ZHITOMIR REGION.

Construction of a CHP with the installation of a Buttner waste heat boiler with a capacity of P = 75 MW

DOK "KALEVALA" PETROZAVODSK. KARELIA

DOK "KALEVALA" PETROZAVODSK. KARELIA

Construction of a CHP with installation of a Buttner waste heat boiler with a capacity of P = 50 MW on wood waste.

"BIOTES" LLC RAKHOV

"BIOTES" LLC RAKHOV

Turnkey construction of Bio TPP with installation of a steam boiler unit HURST BOILER 32 tons of steam / hour (fuel chips) and a turbine unit Р = 6 MW.

"IGOREVSKY DOK" ZD MDF PLIT  IGOREVSKAYA

"IGOREVSKY DOK" ZD MDF PLIT IGOREVSKAYA

Construction of a CHP with the installation of a Buttner waste heat boiler with a capacity of P = 75 MW on wood waste.